Cir. 13/1968

Design of Sand Bunkers

Department
Not stated
Year
1968
Collection
Regulation-wise digest (to 2017)
Under
CMR 100 / MMR107
In the DGMS Circulars (up to June 2017) compilation, p. 247.
Open PDF at page 247

10. Design of Sand Bunkers—Some fatal accidents in sand stowing bunkers have occurred in the past while persons were engaged inside bunkers for releasing stuck up sand. If a bunker is well designed normally there should be no need for a person to go inside it to dislodge sand. But in the case of some old sand bunkers sometimes need may arise to dislodge stuck up sand or lead sand. This should be achieved not by sending a man inside the bunker but by directing a jet of water or by operating a rake from outside the bunker. Where however, it is imperative to send a man inside the bunker, it is recommended that the operation should be conducted under competent supervision and that adequate precautions such as the use of a strong steel rope anchored on surface to provide the persons with necessary hand hold, use of a safety belt etc. are taken. It may also be advisable to fix 'U' brackets at convenient places inside the bunker to serve as steps for persons to go inside a bunker.

At one mine when a workman was partly buried in sand in a sand bunker and there was risk of sand drowning him completely if disturbed, a large diameter pipe (1 metre) was lowered around him and sand from within the pipe removed. Finally the man was saved and brought to surface.

It is understood that sand bunkers of different types, sizes and shapes in use in our many mines call for a different set of precautions in each case. Therefore, the stowing installation at mines should be carefully studied and in the light of foregoing remarks the procedure to deal with dangerous situation laid down.

(Cir. 13/1968)