Cir. 19/1967

Emergency door seals in preparatory stoppings

Department
Not stated
Year
1967
Collection
Regulation-wise digest (to 2017)
Under
CMR 100 / MMR107
In the DGMS Circulars (up to June 2017) compilation, pp. 243–247.
Open PDF at page 243

Part of this text was machine-read from a scanned page and may contain recognition errors. Check the original page before relying on it.

9. Emergency door seals in preparatory stoppings—It has been recommended that every preparatory slopping around a depillaring area should be fitted with steel door which can be shut off immediately in the event of symptoms of spontaneous heating or outbreak of fire.

An effective manner of quickly isolating an area is by providing an emergency door seal consisting of reinforced cement slabs, which can be readily pushed home within a steel frame work- previously built in a preparatory slopping. The constructional details of one such type of seal, which has been successfully PIPE SEN.

COMPLETE S'.A3S EMERGENCY DOOR SEAL sun adopted in one of the mines in Raniganj Coalfield, are given in the note below. As would be noted it docs not take more than 10 minutes to complete this seal by one person. The dimensions of the seal may be altered to suit local requirements. When there is rail track in the gallery containing preparatory stopping, the part of the rail track in the opening of the preparatory slopping should be so fitted as to be readily removable. If the gallery is very wide the emergency door seal may preferably be made of two parts.

A NOTE ON EMERGENCY DOOR SEAL Constructional Details—Constructional details of one Emergency Door Seal provided at a Colliery in Raniganj Coalfield (as on 1965) are shown in the sketches.

The door consists of a fabricated steel frame of 3"x3"xl/4" angle steel and a number of r.c.

slabs sliding within the steel frame work. The sides of slabs are grooved for making bounded joints in order to eliminate leakage of air. The r.c. slabs are 6' 41/2” high x 1' 1" wide x 1 1/2" thick with 1" wide grooves for overlapping. When pushed home the slabs over-lap the frame 11/2" on the sides and top, and 3" at the bottom. The gap between the front and back angle irons of the frame is 13/4" which allows the slabs to fit in snugly.

The reinforcement of the slabs consists of 3/8" m.s. rods placed longitudinally three inch apart with similar rods placed transversely 9" apart. All these rods are welded to each other in position thus giving desired rigidity. A hand rod is welded in position to the reinforcement of each slab for easy handling of the slabs. The last slab is provided with the two hand rods for convenience of operation for ready identification.

All the slabs are numbered serially in the order in which they are to be pushed home. Eight slabs are required in a door of this size.

Materials Required—Materials required for making one door are as follows:

A. Frame:

(i) 3"x3"xl/4" angle Iron for frame-4 pcs each 6'3" long, 25'-0".

(ii) 3"x3"xl/4" angle Iron for bracing-4 pcs 9'6" each long. 38'-0"

(iv) 3"x3"xl/2" angles corners 8 pcs each 3" 2'-0" (v)

2"x4"xl/4" channel iron for bottom-1 pc 10'-0" 75'-0" B. Slabs:

(i) Reinforcement of 3/8" rods 9x42' for each slabs-378 ft.

(ii) Cement—Two bags.

(iii)Sand—Two bags.

(iv) Stone chips or ash cinders four bags (l/8"xl/2")

Cost:

1. Cost of materials:

For iron materials—Total 186 kg @ Rs. 800/- per tonne = Rs.150.00 For other materials—" " " " " " = Rs. 24.00

2. Labour Cost Framework—Rs. 25/- L.S.

Slabs @ Rs. 6/- each Rs. 54/- Total Rs. 79.00 Grand Total Rs. 253.00 Time required for emergency sealing—At each preparatory door site a ready made mixture of cement and sand in a bag and sufficient quantity of water in a tank are kept readily available for eliminating delay in sealing. It lakes about 4 minutes in pushing home all the door slabs in position and another 3 to 5 minutes for applying the cement plaster in all joints to make an absolutely air light seal. Thus the sealing operation is completed in less than 10 minutes, the whole job being done by one person.

Strengthening of the seal—Once the sealing of the door is completed, further strengthening can be done at the earliest opportunity by erecting brick-work on the outside of the door. For this purpose outer sides of the slabs as well as the plaster of the preparatory stopping are made rough by checked lines for good bonding. 3/8" rods projecting out of the slabs may also be welded on to the reinforcement rods for better bonding.

Sampling pipes etc.—Two sampling pipes, one for black damp and the other for fire damp, and one water seal pipe are welded to the steel frame of the door thus ensuring that these important items are not forgotten at the lime of actual emergency.

A removable lock is also provided at the bottom member of the frame for locking the last slab as shown in the sketch. The last slab may or may not be locked depending on the nature of atmosphere inside the seal. The last slab may be kept unlocked for providing an easy outlet in case of an explosion inside the seal in which case the last slab may act as a 'relief valve'. A duplicate slab is provided for replacing the damaged slab in such an event.

a suitably designed rack is provided near the site of the preparatory stopping for orderly storage of the numbered slabs, a mixture of sand and cement in plastic bags, water, and implements for completing the seal.

(Cir. 19/1967)