5. Lowering heavy material in cages—Investigation into a few incidents of overwind in shafts has revealed that while lowering heavy loads like props, machinery etc. in the shaft, care was not taken to suitably balance the load in the other cage to eliminate unbalance as far as possible and the descending cage was landed roughly with speed and the ascending cage was over wound causing at times damage to the headgear and its fittings. In winding installations where automatic contrivances are fitted and are maintained in proper working order even though an overwind may be averted yet the winding ropes and the cage suspension gears can be subjected to a heavy shock load due to sudden braking of the drum while running at a high speed.
In order that such accidents-are averted, following precautions shall be taken and necessary written instructions to persons concerned shall be issued: — (1) Heavy loads should not be lowered except under the supervision of a competent person who will ensure that the material is properly secured in the cage.
(2) Before lowering the loaded cage he shall ensure that the other cage has been suitably loaded for balance.
(3) The competent person supervising the operation shall be present till the completion of entire operation including unloading in a midset when the same is required to be done.
(Cir. 32/1968)