8. The need for good construction of high walls—In a fatal accident a 18m long x 4.5m high x 38cm thick wall on one side of an incline cutting collapsed after two weeks of its construction on a loader. The wall was made up of brick in cement mortar of a ratio 1: 8 and was built on the stone floor of the incline cutting. The space between the back of walls and sides of the cutting was filled with sand and weep holes were also provided in the brickwork.

The basic defect that led to collapse of the wall was lack of deep and secure foundation commensurate to the total height. Further as a good civil engineering principle, the ratio of cement to sand should not have been less than 1: 4.

Constructing high walls without proper and secure foundation and with poor cement: sand ratio mortar is hazardous. This may be noted and it may always be ensured that such construction is under supervision and control of a competent and qualified (civil) engineer.

(Cir. 40/1971)