Cir. Tech. 14/1982
Skip winding equipment in inclined shaft/winze
- Department
- Technical
- Year
- 1982
- Collection
- Regulation-wise digest (to 2017)
- Under
- CMR 75/MMR 82
2. Skip winding equipment in inclined shaft/winze—In respect of the Skip Winding installation in an inclined Shaft/Winze, the following guidelines be adopted with immediate effect: - (1) The life of draw bars and hangers of the skip/conveyance shall not be more than three years if they are made of mild steel as per I.S. 226.
(2) No winding rope shall be used or continued in use if the static factor of safety is less than ten times the maximum static load.
(3) The haulage track of skips/conveyances shall also be provided in accordance with Reg.
83(2) (a) and shall be examined in accordance with Reg. 91(1) (b) (ii) of MMR 1961. Report of such examination shall be maintained in accordance with Reg. 91(2).
(Cir. Tech. 14/1982)