Cir. Tech. 6/1976
Classification of coal seams according to degree of gassiness and procedure for gas surveys
- Department
- Technical
- Year
- 1976
- Collection
- Regulation-wise digest (to 2017)
- Under
- CMR 116
2. Classification of coal seams according to degree of gassiness and procedure for gas surveys—All coal seams are now treated as gassy and they are classified into three degrees of gassiness as defined in Reg.
2(12A) of the Coal Mines Regulations, 1957.
2.0 A seam once classified as Degree I, Degree II or III may be reclassified into higher or lower degree of gassiness depending upon the percentage of inflammable gas in the general body of air and/or the rate of emission of such gas in cubic metres per tonnes of coal raised. For this purpose, sub-regulation (5) of Reg. 116 of the CMR 1957 requires the mine managements to examine, once at least in thirty days, the rate of emission of inflammable gas in cubic metre per tonne of coal raised as also the percentage of inflammable gas in the general body of air.
3.0 As regards determination of rate of emission of inflammable gas in cubic metre per tonne of coal raised, the standard procedure to be adopted is given in Appendix I to this circular.
4.0 Even though in Degree I gassy seams the rate of emission of gas is usually almost negligible, it is advisable to keep a close watch on the gas behaviour pattern of such seams, and for this purpose it is recommended that the procedure given in Appendix II for collection of additional data regarding gassiness should be strictly followed.
5.0 It is further advised that results of every bore hole gas survey in a degree I gassy mine should be promptly conveyed to the JDMS concerned. Incidentally, the results of every examination made in pursuance of sub-regulation (5) of regulation 116 are to be recorded in a bound paged book kept for the purpose as provided therein.
6.0 This supercedes DGMS Circular Nos. 3 of 1969 and 21 of 1970.
APPENDIX I DETERMINATION OF RATE OF EMISSION OF INFLAMMABLE GAS PER TONNE OF COAL FOR THE PURPOSE OF CLASSIFICATION OF GASSY SEAMS
1. Place and Time of Collection of air samples
(a) The air samples shall be collected at the following points:
(i) at the outbye end of the return airway of every ventilating district;
and
(ii) at the outbye end of main return.
(b) The samples shall be collected during coal getting operations when the emission of gas is likely to be the maximum taking into account the method of extraction,
2. Method of collection of air samples Air samples shall be collected over the entire cross sectional area of the return airway moving the sampling bottle more or less in the same manner as an anemometer is moved during an air measurement. The air samples may be collected dry, or by water displacement when they are going to be analysed within 72 hours.
3. Analysis of air samples Two air samples shall be analysed for inflammable gas as early as possible, but definitely within 4 days of collecting them.
4. Air measurements The quantity of air passing through the return airways shall be measured at about the same time when an air sample is collected therein. Each air measurement shall be taken for a time of at least 2 minutes.
5. Calculation for determination of rate of emission of gas G The make of inflammable gas in cubic metres per min = Quantity of air in cubic metres per min * Percentage of inflammable ———————— The rate of emission of inflammable gas in cubic metres per tonne of coal produced G x 60 x 24 Output of coal m tonnes during the day The rate of emission of gas shall be calculated in the above manner separately for each ventilation district and also for the entire mine as obtained from the main return. For fixing the degree of gassiness of a seam the maximum value of the above readings shall be considered.
APPENDIX II GAS SURVEY IN FIRST DEGREE GASSY SEAMS
1. General Determination for presence of inflammable gas shall be made in General Body of Air and in Boreholes.
Detection of Inflammable gas in borehole provides a valuable guideline as to how a seam is potentially behaving in respect of gassiness and therefore due importance to gas survey in boreholes should be given.
2. Procedure
(a) General Body of Air—Sample of air shall be taken from the following vulnerable points:
(i)
Cavities (ii)
Blind headings both in working and disused areas.
(iii) Places in the vicinity of faults, dykes and other geological disturbances.
(b) Boreholes—
(i) For the purpose of gas survey, boreholes shall be drilled at number of active development faces or in the pillar sides adjacent to same, so however that at least one set of boreholes shall be put in a block of coal measuring 45 m x 45 m A set of boreholes at such a working face shall consist of 2 or more number of rising boreholes (one metre apart in vertical plane) so positioned as to intersect almost the whole of the working section of the seam. When thickness of seam is more than the working height, additional borehole(s) shall be drilled in the roof and/or floor coal, as the case may be.
(ii) Air samples shall be taken from inside the boreholes put in as mentioned above specially drilled for the purpose. These boreholes shall be drilled by electric drills at least 1.5 m long and slightly rising. They shall be kept effectively plugged for not less than 60 minutes before collecting samples. The air sample from the back of such boreholes shall be collected by inserting a copper/brass tube and sucking the sample by water displacement in a 100 c.c. glass tube provided with two-way stop cocks at its ends.
(iii) Air samples shall again be collected from the same borehole after keeping them plugged for 7 days.
3. Periodicity
(a) Initially, in every seam as soon as it is opened or reopened.
(b) While approaching within 30 metres of a fault plane, dyke or other geological disturbances.
(c) Determination in general body of air shall be made at least once in thirty days. Borehole sample shall be collected at suitable intervals to be fixed by the manager, but not less than once in a quarter.
4. Recording and intimation of results etc.
(a) Results of borehole gas survey shall be recorded in bound paged book.
(b) Whenever any inflammable gas is found either in a borehole or general body of air a copy of the entries made in the above-said register shall be promptly sent to the concerned Joint Director.
(c) A separate plan of workings shall be maintained showing the position of the boreholes, last date of gas survey, and other relevant information including points where 2% or more inflammable gas has been found in a borehole.
(Cir. Tech. 6/1976)